Elderly's Home at Jat Min Chuen Chung Yuet Lau

大埔白石角科學園
相片由香港科技園公司提供

香港科技園公司創新斗室是香港其中一個採用「組裝合成」建築法的先導計劃。項目提供約500個床位。房間類型包括單人工作室、雙人工作室、共居工作室及套房(與住宅單元結合在一起的娛樂和共享生活 / 工作空間),並提供輔助配套設施。創新斗室將會成為一個智能生活及匯聚創新協作的社區。

17層高的大樓座落於香港科學園東南面,佔地32,000平方尺,由418個組件組裝而成,並提供5種類型的房間。

香港科技園公司於2021年4月7日宣布創新斗室正式開幕。

 

相關新聞:

07/04/2021 香港科技園公司

香港科技園公司INNOCELL開幕 為創科社群提供智能生活及協作空間 持續推動本港創科發展

Public Annoucement Date on Use of MiC

May 2018

Construction Commencement Date

Dec 2018

Modules Manufacturing Date

Oct 2019

Module Installation Commencement Date

Jan 2020

Date of Completion

Q4 2020

種類 描述 長度(毫米) 闊度(毫米) 高度(毫米) 內部面積(平方米) 組件重量(噸) 數量

CO

Coliving

7350

3100

3050

23

Approx 22

120

ST

Standard Studio

7350

3100

3050

23

Approx 22

206

SS

Sleepbox Studio

7350

3100

3050

23

Approx 22

39

FA

Family Unit (Paired Modules)

7350

3100

3050

23

Approx 22

52

0

其他

7350

3100

3050

23

Approx 22

1

Learn more about the project

WSP (HK) Limited, the Structural Engineering Consultant of the InnoCell Project, has won a merit award in the Hong Kong Institution of Engineers (HKIE) Innovation Awards 2020 (Category I – An Invention) for their Innovative MiC Design Approach for InnoCell.

Due to the innovation and environmental sustainability in architecture and design, InnoCell has received Rethinking The Future Awards 2020 - Second Award. The project stands out among 1,500+ entries. Click here for more information about the award.

By leveraging the Building Information Modelling (BIM) technology in this project, the project team - Hong Kong Science & Technology Parks Corporation, Hip Hing Engineering Company Limited, and Leigh & Orange Limited, has won the Autodesk Hong Kong BIM Awards 2020. For their video, please click here.

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case. The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page.

Last Updated: 27.01.2026 12:22:20

Transitional Housing Projects

In order to relieve the acute shortage of housing, the HKSAR Government announced the three-year transitional housing target of 15,000 units in January 2020. Up to now, two MiC transitional housing projects were completed, including the Nam Cheong 220 by The Hong Kong Council of Social Service and the Junction of Sung Wong Toi Road and To Kwa Wan Road Project by Lok Sin Tong. United Court by Sheng Kung Hui will be commenced shortly. The largest project in Kong Ha Wai by Pok Oi Hospital was commenced in March 2021. Over 6,000 people will be homed by the end of 2022.

Update on the Progress of Supplying Transitional Housing

08.07.2021 Legislative Council of the HKSAR

江夏圍過渡性房屋計劃 - 首批示範單位落地元朗 (Chinese only)

10.06.2021 AluHouse

樂善堂社會房屋計劃「樂屋」 - 宋皇臺道及土瓜灣道交界組合屋項目 (Chinese only)

03.06.2021 Lok Sin Tong

江夏圍過渡性房屋項目正式動土 (Chinese only)

10.05.2021 City's Time

HOT TOPIC