Chinese Medicine Hospital in Tseung Kwan O

沙田乙明邨
相片由香港房屋協會提供

香港房屋協會於沙田乙明邨羽毛球場,以「組裝合成」建築法(MiC) 興建一幢樓高10層的長者屋,提供64個面積約200平方呎的單人房單位供70歲以上長者入住。樓宇命名為「松悅樓」,寓意入住的長者長壽健康、充滿喜悅。

這是房協首個MiC項目,大樓地面及1樓將以傳統鋼筋及混凝土方法建造;2樓至9樓的住宅樓層將以鋼結構MiC方法興建。

期望透過工程的落成,有效地利用公共房屋資源,以支持行政長官在《 2018年施政報告》中提出的關於MiC的新倡議 。

 

相關新聞:

13/04/2021  香港房屋協會

房協首個「組裝合成」長者房屋項目正式簽署上蓋工程合約

Courtesy of HKHS

Highlights on Current Status

Foundation Works and Mock up Module Fabrication

Project Current Status

Foundation Works

No. of MiC Modules

136

CFA (m²)

2,733

MiC CFA (m²)

1,719

Superstructure Storeys

10

MiC Storeys

8

Anticipated Construction Cycle of Typical MiC Floor (@ Day cycle)

TBA

Construction Commencement Date

Q2 2020

Anticipated Date of Completion

Year of 2023

Structure

Steel

Public Announcement Date on Use of MiC

Mar 2019

Construction Commencement Date

Q2 2020

Anticipated Foundation Works Completion Date

Q3 2021

Anticipated Date of Completion

Year of 2023

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case. The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page.

Last Updated: 27.01.2026 12:54:06

Transitional Housing Projects

In order to relieve the acute shortage of housing, the HKSAR Government announced the three-year transitional housing target of 15,000 units in January 2020. Up to now, two MiC transitional housing projects were completed, including the Nam Cheong 220 by The Hong Kong Council of Social Service and the Junction of Sung Wong Toi Road and To Kwa Wan Road Project by Lok Sin Tong. United Court by Sheng Kung Hui will be commenced shortly. The largest project in Kong Ha Wai by Pok Oi Hospital was commenced in March 2021. Over 6,000 people will be homed by the end of 2022.

Update on the Progress of Supplying Transitional Housing

08.07.2021 Legislative Council of the HKSAR

江夏圍過渡性房屋計劃 - 首批示範單位落地元朗 (Chinese only)

10.06.2021 AluHouse

樂善堂社會房屋計劃「樂屋」 - 宋皇臺道及土瓜灣道交界組合屋項目 (Chinese only)

03.06.2021 Lok Sin Tong

江夏圍過渡性房屋項目正式動土 (Chinese only)

10.05.2021 City's Time

HOT TOPIC